Trestle Trail Bike Path
Document Description | Date |
---|---|
Limited Subsurface Soil and Groundwater Investigation | 11/17/2008 |
Notification of Release | 5/5/2010 |
Letter of Responsibility | 5/21/2010 |
VHBs Response to Public Comments | 8/18/11 |
DEM and VHBs Collective Response to Public Comments | 9/20/11 |
Site Investigation Report Addendum | 1/24/12 |
SIR Comments | 2/2/12 |
Response to RIDEM SIR Comments | 3/2/12 |
SIR Comments | 3/7/12 |
Response to RIDEM SIR Comments | 3/7/12 |
Program Letter | 3/21/12 |
Post-SI Public Notice | 3/30/12 |
Remedial Decision Letter | 5/30/12 |
Remedial Action Work Plan | 8/2012 |
Final Revised Report | 2/1/13 |
Response to RWP Comments | 2/1/13 |
Remedial Approval Letter | 2/18/13 |