Providence Gas Co.-AA (a.k.a. Former New England Gas Company MGP)

642 Allens Avenue, Providence, Rhode Island

This Document Index was established in September 2016. As such, many older documents related to this site are currently only available in hard copy, and are not found on this page. If you wish to complete a review of all documents related to this site, please request a file review with RIDEM's Office of Customer and Technical Assistance. Instructions on how to file such a request can be found here.

Document Description Date
HEI - Underground Storage Tank Closure Assessment 10/xx/1995
RCA - Remedial Action Report for Condensate Tank Closure - Compressor Building No. 2 10/20/1995
RCA - Remedial Action Report for Short Term Measure 6/14/1996
HEI - Underground Storage Tank Closure Assessment 9/xx/1998
ESS - Subsurface Investigation and Proposed Remediation 10/21/1999
Prov Gas Co. - Summary Letter 4/13/2001
VHB - Remdial Action Closure Report 11/15/2002
VHB - Remdial Action Closure Report 12/xx/2002
VHB - Site Investigation Report 4/8/2003
GZA - Short Term Response Action Plan (STRAP) - Holder 18-21 Capping Project 4/27/2016
GZA - Short Term Response Action Plan (STRAP) Addendum - Holder 18-21 Capping Project 5/10/2016
RIDEM - SHort Term Response Action Approval Letter - Holder 18-21 Capping Project 5/18/2016
GZA - Proposed Upcoming Groundwater Monitoring Activities 5/26/2016
GZA - Short Term Response Action Plan (STRAP) - Dike Access Road 6/29/2016
GZA - SHort Term Response Action Plan (STRAP) Addendum - Dike Access Road 8/22/2016
RIDEM - SHort Term Response Action Approval Letter - Dike Access Road Project 8/25/2016
RIDEM - Office of Water Resources Approval Letter - Dike Access Road Project 8/29/2016
RIDEM - Public Involvement Plan Process Inititation Letter with attached PIP Petition 9/6/2016
GZA - Proposed Schedule for the PIP Development Process 9/15/2016
Hinckley Allen - Legal Memorandum - Liquefaction Project 9/26/2016
GZA - Updated Schedule - Draft PIP Development Process 9/30/2016
RIDEM - RIDEM Legal Response to Hinckley Allen Liquifaction Memo & PIP 10/21/2016
GZA - Draft Public Involvement Plan with attachments 10/28/2016
No LNG in PVD - Open Letter to RIDEM about National Grid's proposed Fields Point Liquefaction Facility 11/1/2016
Alston & Bird LLP - Letter to FERC - Supplemental Information related to Liquefaction Project Resource Report 7 and the Soil Management Plan 11/16/2016
RIDEM - Office of Customer & Technical Assistance - Meeting Summary Letter 1/10/2017
FERC - Letter to RIDEM regarding 10-21-16 Letter fron RIDEM to National Grid 1/17/17
No LNG in PVD - Federal Consistency Review Comments to RICRMC 1/23/17
No LNG in PVD - Follow up Letter to RIDEM 2/10/17
FERC - Environmental Data Request Letter to National Grid 4/7/17
Alston & Bird LLP - National Grid Response Letter to FERC 4-7-17 Request Letter 4/12/17
No LNG in PVD - Comment Letter to FERC about National Grid's proposed Fields Point Liquefaction Facility 4/24/17
RICRMC - Amended Agreement to Stay Six Month Review Period between RICRMC and National Grid 4/25/17
GZA - Short Term Response Action (STRA) Completion Report - Holder 18/21 Capping Project 4/27/17
GZA - Draft Public Involvement Plan with attachments - Version 2 5/4/17
GZA - Short Term Response Action Plan (STRAP) - Proposed Liquefaction Project 5/12/17
GZA - Short Term Response Action Plan (STRAP) Addendum - Holcim Driveway 5/30/17
RIDEM - Public Involvement Plan (PIP) Comment Letter 6/2/17
GZA - Response to Comments - Public Involvement Plan (PIP) 6/9/17
GZA - Final Public Involvement Plan with attachments (Version 3) 6/9/17
National Grid - Public Meeting Notice - Technical Information Session - English 6/23/2017
National Grid - Public Meeting Notice - Technical Information Session - Spanish 6/23/2017
RIDEM - Public Involvement Plan (PIP) Approval Letter 6/28/2017
National Grid - Public Notice - Established Informational Repository - English & Spanish 7/7/2017
National Grid - Second Public Meeting Notice - English, Spanish, Portuguese & Khmer 7/26/2017
RIDEM - Request to National Grid for Response to Public Comments on the STRAPs 8/18/2017
GZA - Meeting Summary, Response to Public Comments & Additional Clarifications - STRAP: Proposed Liquefaction Project, STRAP Addendum: Holcim Driveway 10/5/2017
RIDEM - Letter Response to STRAP Public Comments 10/6/2017
RIDEM - Liquefaction STRAP Comment Letter 10/6/2017
No LNG in PVD - Email to RIDEM regarding National Grid’s proposed STRAPs 10/10/2017
GZA - Short Term Response Action Plan (STRAP) Addendum - Proposed Liquefaction Facility 10/11/2017
RIDEM - Response Letter to No LNG in PVD's 10-10-17 email 10/13/2017
No LNG in PVD - Letter to Governor Raimondo regarding National Grid’s proposed Liquefaction STRAP 10/16/2017
RIDEM - Short Term Response Action Approval Letter - Liquefaction Facility Area 10/27/2017
No LNG in PVD - Appeal of Approved Short-Term Response Action 11/22/2017
GZA - Notification of Maintenance and Repair Projects 3/8/2018
Notice of Public Meeting for Water Quality Certification Application

National Grid Letter/Application 9/12/16

National Grid Letter/Application 4/4/17
3/30/2018
RIDEM Office of Water Resources - Letter to National Grid 3/30/2018
RIDEM - Administrative Adjudication Division - Decision and Order 5/18/2018
FERC - Order Issuing Certificate 10/17/2018
Notice of Water Quality Certificate and Response to Comments



Supporting Documentation:

- Public Comment re: Water Quality Certification (12/4/17)

- RIDEM - Request for Additional Information (3/30/18)

- National Grid - Response to Request for Additional Information (7/20/18)

- RIDEM - Request for Additional Information (9/5/18)

- National Grid - Response to Request for Additional Information (10/25/18)
11/21/2018
National Grid - Fields Point Liquefaction Project - Monthly Status Report for November 2018 12/3/2018
Providence - Soil & Erosion Control Plan Approval 12/10/2018
GZA - Notification to Start Work – Liquefaction STRAP Project 12/28/2018
GZA - Notice to Abutters and/or Interested Parties (English, Spanish, Portuguese, Cape Verdean Creole and Khmer) 12/28/2018
GZA - Notification of Public Involvement Plan Sign Posting 1/2/2019
GZA - Notification of Maintenance & Repair Projects 1/8/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for December 2018 1/8/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-7-19 1/14/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-14-19 1/21/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-21-19 1/28/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for January 2019 2/1/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-28-19 2/4/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-4-19 2/11/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-11-19 2/18/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-18-19 2/25/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for February 2019 3/1/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-25-19 3/4/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-4-19 3/11/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-11-19 3/18/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-18-19 3/25/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-25-19 4/1/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for March 2019 4/1/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-1-19 4/8/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-8-19 4/15/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-15-19 4/22/2019
GGZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-22-19 4/29/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for April 2019 5/1/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-29-19 5/6/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-6-19 5/13/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-13-19 5/20/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-20-19 5/27/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-27-19 6/3/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for May 2019 6/3/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-3-19 6/10/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-10-19 6/17/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-17-19 6/24/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-24-19 7/1/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-1-19 7/8/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for June 2019 7/8/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-8-19 7/15/2019
GZA - Notification of Upcoming Maintenance Activities 7/22/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-15-19 7/22/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-22-19 7/29/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for July 2019 8/1/2019
National Grid - Email Notification of Emergency Gas Line Repair 8/1/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-29-19 8/5/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-5-19 8/13/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-12-19 8/19/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-19-19 8/26/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for August 2019 9/3/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-26-19 9/3/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-2-19 9/9/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-9-19 9/16/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-16-19 9/23/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-23-19 9/30/2019
GZA - Notification of Maintenance and Repair Projects 10/1/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for September 2019 10/1/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-30-19 10/7/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-7-19 10/15/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-14-19 10/21/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-21-19 10/28/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for October 2019 11/1/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-28-19 11/4/2019
GZA - Notification of Maintenance and Repair Project - Junction Box Support Installation 11/7/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-4-19 11/12/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-11-19 11/18/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-18-19 11/25/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-25-19 12/2/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for November 2019 12/2/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-2-19 12/9/2019
GZA - Application for CRMC Maintenance Certificate for Bulkhead Maintenance Repairs 12/16/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-9-19 12/16/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-16-19 12/23/2019
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-23-19 12/30/2019
National Grid - Fields Point Liquefaction Project - Monthly Status Report for December 2019 1/2/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-30-19 1/6/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-6-20 1/13/2020
GZA - Dike Access Road STRAP Completion Abutter Notification Fina - All Languages 1/17/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-13-20 1/21/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-20-20 1/27/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-27-20 2/3/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for January 2020 2/3/2020
GZA - Short Term Response Action (STRA) Completion Report - Dike Access Road Project 2/7/2020
GZA - Notice of Termination (NOT) – WQC No. 16-115 and RIPDES RIR101439 - Dike Access Road 2/7/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-27-20 2/10/2020
GZA - Bottom Sediment Sampling and Analysis, Proposed Drywell Closure Plan 3/10/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-9-20 3/16/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-10-20 2/17/2020
GZA - Proposed Drywell Closure Plan 2/19/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-17-20 2/24/2020
GZA - Notification of Maintenance and Repair Projects 2/28/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for February 2020 3/2/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-24-20 3/2/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-2-20 3/9/2020
RIDEM - Drywell Closure Plan Approval Letter 3/23/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-16-20 3/23/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-23-20 3/30/20
National Grid - Fields Point Liquefaction Project - Monthly Status Report for March 2020 4/1/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-30-20 4/6/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-6-20 4/13/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-13-20 4/20/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-20-20 4/27/2020
GZA - Notification of Maintenance and Repair Projects 5/1/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for March 2020 5/1/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-27-20 5/4/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-4-20 5/11/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-11-20 5/18/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-18-20 5/26/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-25-20 6/1/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for May 2020 6/1/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-1-20 6/8/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-8-20 6/15/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-15-20 6/22/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-22-20 6/29/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for June 2020 7/1/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-29-20 7/6/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-6-20 7/13/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-13-20 7/20/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-20-20 7/27/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-27-20 8/3/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for July 2020 8/3/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-3-20 8/11/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-10-20 8/17/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-17-20 8/24/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-24-20 8/31/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for August 2020 9/1/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-31-20 9/8/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-7-20 9/14/2020
GZA - Notification of Maintenance and Repair Projects 9/15/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-14-20 9/21/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-21-20 9/28/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for September 2020 10/1/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-28-20 10/5/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-5-20 10/12/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-12-20 10/19/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-19-20 10/26/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-26-20 11/2/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for October 2020 11/2/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-2-20 11/9/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-9-20 11/16/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-16-20 11/23/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-23-20 11/30/2020
National Grid - Fields Point Liquefaction Project - Monthly Status Report for November 2020 12/1/2020
GZA - Unanticipated Bypass Notification 11/25/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-30-20 12/7/2020
National Grid - Fields Point Liquefaction Project - Certificate Extension Request 12/8/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-7-20 12/14/2020
FERC - Fields Point Liquefaction Project - Notice of Request for Extension of Time 12/15/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-14-20 12/21/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-21-20 12/28/2020
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-28-20 1/4/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for December 2020 1/4/2021
ERC - Fields Point Liquefaction Project - Grant of Request for Extension of Time 1/11/202 1/7/2021
GZA - Monitoring Report - 2014-2017 with Attachments 1/7/2021
GZA - Monitoring Report - 2018 with Attachments 1/7/2021
GZA - Monitoring Report - 2019 with Attachments 1/7/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-4-21 1/11/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-11-21 1/19/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-18-21 1/25/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for January 2021 2/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-25-21 2/1/2021
GZA - Notification of Maintenance and Repair Projects 2/5/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-1-21 2/8/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-8-21 2/15/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-15-21 2/22/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for February 2021 3/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-22-21 3/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-1-21 3/8/2021
GZA - Monitoring Report - 2020 with Attachments 3/9/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-8-21 3/15/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-15-21 3/22/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-22-21 3/30/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for March 2021 4/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-29-21 4/5/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-5-21 4/12/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-12-21 4/19/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-19-21 4/26/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for April 2021 5/3/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-26-21 5/3/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-3-21 5/10/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-10-21 5/17/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-17-21 5/24/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for May 2021 6/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-24-21 6/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-31-21 6/7/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-7-21 6/14/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-14-21 6/21/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-21-21 6/28/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for June 2021 7/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-28-21 7/6/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-5-21 7/12/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-12-21 7/19/2021
GZA - Replacement Monitoring Wells Installation Work Plan 7/22/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-19-21 7/26/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for July 2021 8/2/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 7-26-21 8/2/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-2-21 8/9/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-9-21 8/16/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-16-21 8/23/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-23-21 8/30/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for July 2021 9/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 8-30-21 9/6/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-6-21 9/13/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-13-21 9/20/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-20-21 9/27/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for September 2021 10/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 9-27-21 10/4/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-4-21 10/11/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-11-21 10/18/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-18-21 10/25/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for October 2021 11/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 10-25-21 11/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-1-21 11/8/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-8-21 11/15/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-15-21 11/22/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-22-21 11/29/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for November 2021 12/1/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 11-29-21 12/6/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-6-21 12/13/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-13-21 12/20/2021
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-20-21 12/27/2021
National Grid - Fields Point Liquefaction Project - Monthly Status Report for December 2021 1/4/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 12-27-21 1/4/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-3-22 1/10/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-10-22 1/18/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-17-22 1/24/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-24-22 1/31/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for January 2022 2/1/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 1-31-22 2/7/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-7-22 2/14/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-14-22 2/22/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-21-22 2/28/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for February 2022 3/1/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 2-28-22 3/7/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-7-22 3/14/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-14-22 3/21/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-21-22 3/28/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for March 2022 4/1/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 3-28-22 4/4/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-4-22 4/11/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-11-22 4/18/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-18-22 4/25/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for April 2022 5/2/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 4-25-22 5/2/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-2-22 5/9/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-9-22 5/16/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring Demobilization 5/19/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-16-22 5/23/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-23-22 5/31/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for May 2022 6/1/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 5-30-22 6/6/2022
GZA - Notification of Maintenance and Repair Projects 6/7/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-6-22 6/13/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-13-22 6/21/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-20-22 6/27/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for June 2022 7/1/2022
GZA - Liquefaction STRAP Perimeter Air Quality Monitoring (AQM) Results – Week of 6-27-22 7/5/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for July 2022 8/1/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for August 2022 9/1/2022
Rhode Island Energy - Annual Monitoring Report - 2021 9/9/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for September 2022 10/3/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for October 2022 11/1/2022
National Grid - Fields Point Liquefaction Project - Monthly Status Report for November 2022 12/1/2022
National Grid - Replacement Monitoring Wells Installation Work Plan 12/27/2022
GZA - Notification of Maintenance and Repair Projects 2/8/2023
GZA - Fields Point Liquefaction Project (FPLP) Short Term Response Action (STRA) Closure Report 3/21/2023
GZA - Notification of Maintenance and Repair Projects 4/20/2023
GZA - Annual Monitoring Report - 2022 6/21/2023
GZA - Notification of Maintenance and Repair Projects 6/23/2023
GZA - Notification of Maintenance and Repair Projects 8/23/2023